Germany completes 365-metre wind turbine in former coal region
A wind turbine in Schipkau, Brandenburg, has reached 365 metres, making it the world’s tallest, Euronews reports. Its developers expect it to generate 30–33 gigawatt hours a year, while the project tests whether stronger, steadier winds at height can make wind power viable in less windy parts of Europe.
Bottom line — If connected to the grid as planned in November, the turbine could supply about 7,500 four-person households each year.
Go deeper 6
-
GICON says the turbine’s expected annual output is 220% above that of conventional nearby turbines, with generation costs below €0.05 per kilowatt hour.
-
A telescopic device raised the structure in stages, from 150 metres to 300 metres; the rotor tip brings its total height to 365 metres.
-
Construction stopped in late 2025 after problems were found in steel parts. GICON founder Jochen Großmann said safety and quality had priority.
-
Measurements at a nearby mast showed stronger, steadier winds at 300 metres than at conventional turbine heights, according to Euronews.
-
Germany lost about 9.3 terawatt hours of wind power to grid constraints in 2023, while congestion management cost nearly €3 billion, Tagesspiegel analysis cited by Euronews found.
-
The site is intended to become a hybrid plant combining two levels of wind power with a ground-mounted solar park.